CNY · Cargo cut-off

Chinese New Year shutdown planner

Plan cargo readiness around Chinese New Year, National Day Golden Week, and the rest of the 2026 to 2027 China factory shutdown calendar. The table below shows official holiday dates, typical factory return windows, and the cargo cut-off the forwarder will hold you to.

Last updated 2026-05-08. Math runs in your browser, no data leaves your computer.

General guidance only, not legal or professional engineering advice. Verify against the cited primary sources (IMDG, REACH, ChAFTA, RCEP, Customs Tariff Act, supplier SDS, etc.) before committing to a shipment, declaration, or contract. Sourzi assumes no liability for outcomes based on these calculators.

Next major shutdown

Dragon Boat Festival 2026

42 days from today (8 May 2026). Holiday window: 2026-06-19 to 2026-06-21.

Three-day holiday. Factory return is immediate; ports run light briefly.

春节 2026

Spring Festival 2026

2026-02-17 to 2026-02-23

Factory return: 2026-02-25 to 2026-03-09 (rolling)

Statutory holiday is 7 days; most factories close 7 to 14 calendar days, with full workforce returning 14 to 21 days after end of holiday because of migrant-worker travel back from home provinces. Plan cargo cut-off no later than mid-January 2026 for guaranteed pre-CNY loading.

清明节 2026

Qingming 2026

2026-04-04 to 2026-04-06

Factory return: 2026-04-07

Three-day grave-sweeping holiday. Factory return is immediate, but ports run light for 1 to 2 days. No major cargo-flow disruption.

五一劳动节 2026

Labour Day 2026

2026-05-01 to 2026-05-05

Factory return: 2026-05-06

Five-day holiday. Customs clearance windows reduced; ports run partial. Cargo readiness declarations should leave by 28 April for clean processing.

端午节 2026

Dragon Boat Festival 2026

2026-06-19 to 2026-06-21

Factory return: 2026-06-22

Three-day holiday. Factory return is immediate; ports run light briefly.

中秋节 2026

Mid-Autumn 2026

2026-09-25 to 2026-09-27

Factory return: 2026-09-28

Three-day holiday. Falls one week before National Day in 2026; many factories opt to bridge the two holidays into a 12-day shutdown 25 Sep to 7 Oct. Confirm with each factory individually.

国庆节 2026

National Day Golden Week 2026

2026-10-01 to 2026-10-08

Factory return: 2026-10-09 to 2026-10-12

Statutory 8-day holiday. Most factories close 8 to 12 days; some bridge with Mid-Autumn for 12 to 14 days. Customs runs partial through the holiday and the 1 to 2 days after. Plan cargo cut-off no later than mid-September.

春节 2027

Spring Festival 2027

2027-02-06 to 2027-02-12

Factory return: 2027-02-14 to 2027-02-26 (rolling)

Earlier than 2026 CNY. Plan cargo cut-off no later than first week of January 2027.

Why Spring Festival is different

China runs roughly 200 million migrant workers, most in the manufacturing-heavy coastal provinces (Guangdong, Zhejiang, Jiangsu, Fujian, Shandong) but with home registration (户口) in inland provinces (Sichuan, Anhui, Henan, Hunan, Hubei, Guizhou). Spring Festival is the once-a-year window when the migrant workforce travels back to home villages for family obligations. The migration is logistically vast: 3 billion trips are made over the 40-day extended Spring Festival travel period (春运). Train tickets sell out 30 days before the holiday; flight prices triple; long-distance bus services run at capacity around the clock.

Factories cannot run without the migrant workforce. The official statutory holiday is 7 days but the practical disruption is 14 to 28 days, because workers travel up to 36 hours each way and many use the window for delayed family events (weddings, births, family elder visits) that postpone the return. Factory production lines run 60 to 70 percent staffed on Day 1 of post-CNY, ramp to 90 percent over a week, hit normal output around Day 14. For chemical batch production specifically, QC test cycles run 50 to 100 percent longer than usual for the first 3 to 4 weeks post-CNY because the QC lab is rebuilding the rhythm of the line.

Customs runs at minimum staffing through the holiday and the 1 to 2 days after. Routine declarations take 3 to 5 business days longer than usual. The week before CNY is when delays are worst, because the queue is full of last-minute filers and inspections concentrate on outbound containers. Cargo declarations should land 7 working days before holiday for clean processing, not 1 day before.

Ports run light through the holiday and the first 3 to 5 days after. Vessel calls drop, container yard turnover slows, terminal handling charges sometimes spike on the first 2 days post-holiday because of the demand-supply mismatch. If the cargo can wait two weeks past the holiday, freight is cheaper; if the cargo cannot wait, the surcharge bites.

National Day Golden Week (1 to 8 October) is the second-largest disruption. The migration is shorter and less complete than CNY, but factory production drops to near zero and customs runs partial. The 2026 calendar is unusual because Mid-Autumn falls 25 to 27 September, only days before National Day; many factories bridge the two into a 12-day shutdown 25 September to 7 October. Plan around the bridge, not the official statutory days.

Worked example. The CNY pre-holiday rush

The booking. A US buyer needs 4 containers of fine chemical product to land at LA by mid-March 2026. The factory in Shandong commits to producing the cargo by 25 January, QC by 1 February, ready for collection 3 February. The forwarder books a vessel sailing from Qingdao on 9 February (8 days before CNY, 17 to 23 February). Looks fine on paper.

The failure. The factory hits its production target but falls behind on QC because the QC lab supervisor takes 2 days off for a family obligation in late January and the assistant is not certified to release fine-chemical batches. QC certificates are not issued until 5 February. The forwarder cannot collect a 5 February release for the 9 February sailing, because the inland trucking from Zibo to Qingdao port is fully booked through the pre-CNY rush. Next available trucking is 14 February, two days before CNY closes the road. Customs declaration filed 14 February will not clear before CNY. Either the cargo waits at the port through CNY at demurrage rates, or the booking slips to a post-CNY vessel. Buyer is told the next vessel is 28 February, which now lands at LA late March; 10 to 14 days behind the original schedule.

The fix. On the next pre-CNY shipment, the buyer asks the factory for QC release 30 days before holiday, not 14 days. Cargo is in the factory yard with full documentation by 15 January 2027. Forwarder books a vessel sailing 22 January 2027, two weeks before CNY 2027 (6 to 12 February). The customs declaration files 18 January and clears comfortably before the holiday rush. Cargo lands at LA on schedule. The cost of the 30-day cushion was zero; the cost of the 14-day cushion was the 10 to 14 day delay and the loss of confidence from the buyer customer at destination.

Frequently asked

Why does Chinese New Year cause more disruption than other holidays?

Spring Festival is the once-a-year migration of 200 million migrant workers back to home provinces, mostly inland Sichuan, Anhui, Henan, Hunan. Workers travel 12 to 36 hours each way and many use the holiday for delayed family events (weddings, births, funerals); some return up to 21 days after the official end of holiday. Factories ramp slowly, ports run light. The disruption window is typically 14 to 28 days, far longer than the 7-day statutory holiday.

When should I cut off cargo readiness for CNY?

For guaranteed loading before CNY 2026 (17 to 23 February), cargo should be ready in the factory yard with QC certificates, packing list, and SDS by mid-January. Forwarders bottleneck on container space and trucking the last week before CNY; bookings made after 31 January are common but expensive (peak-season surcharge plus rush fees), and risk slipping into the holiday. The cleanest answer: cargo ready by 15 January, forwarder booking confirmed by 20 January, vessel sailing before 7 February.

What is the post-CNY ramp-up like?

Workers return staggered over 7 to 14 days. Day 1 of the official return is typically 60 to 70 percent staffed; Day 7 is 90 percent; Day 14 is back to normal. QC and packing operations may run slow even at full headcount because the workforce is recalibrating to the production line. For chemical cargo specifically, batch-test results may take 50 to 100 percent longer than usual for the first 3 to 4 weeks post-CNY.

Does customs work during CNY?

GACC customs is staffed at minimum levels through CNY for emergency clearances. Routine declarations take 3 to 5 business days longer than usual through the holiday window. Pre-CNY peak (the last 5 working days before holiday) is when delays are worst because the queue is full of last-minute filers. Plan declarations to land at least 7 working days before holiday for routine clearance.

Are smaller holidays (Qingming, Dragon Boat, Labour Day, Mid-Autumn) worth planning around?

For routine cargo, no. The 3 to 5 day disruption is too short to push a typical 21 to 35 day Asia-US sea lane. For air cargo, courier express, or any time-sensitive shipment, yes. The combination Mid-Autumn plus National Day in 2026 is a particular trap because many factories bridge the two into a 12-day shutdown; routine planning that ignores the bridge will see a clean 12-day delay on the destination side.

How do I confirm whether a specific factory is bridging Mid-Autumn and National Day in 2026?

Ask each factory individually 30 days ahead. Larger factories (1,000+ workers) almost always take the full bridge; smaller factories (under 200 workers) often work through the two-day gap. The factory production schedule is the only authoritative answer.